Nord Stream 2

OSW: Closer to approving the construction of Nord Stream 2

On 31 January, Nord Stream 2 AG (which is 100% owned by Gazprom) obtained the consent of the Mining Authority in Stralsund for the construction and operation of a 55-km long section of the Nord Stream pipeline 2 in Germany. This consent covers both the land section of the pipeline to the town of Lubmin, as well as a section running through German territorial waters, and means that the investor can begin work on the land section – writes Rafał Bajczuk from OSW. 

Obtaining all the necessary permits still requires the consent of the Federal Maritime and Hydrographic Agency in Hamburg on the construction and operation of a gas pipeline in the German exclusive economic zone. The investor expects to receive this consent by the end of March 2018. The first permit for the construction and operation of a gas pipeline on the German continental shelf was granted to the investor in November 2017.

Commentary

There is nothing to indicate that the Federal Maritime and Hydrographic Agency in Hamburg will refuse consent for the construction and operation of the pipeline. The results of the coalition talks between the CDU/CSU and the SPD will also not lead to any changes in Germany’s policy on Nord Stream 2. The only party objecting to the construction of the gas pipeline are the Greens, who stated their negative position during the elections. The decision of the Stralsund Mining Authority has been criticised by both the Greens and environmental NGOs. In addition, on 11 January ecological organisations (including WWF Germany and the Naturschutzbund Deutschland NABU) reiterated an appeal to German politicians demanding that Germany transfer competence to jointly decide on the investment to the European Commission, and that the procedure for approving the construction be repeated. In their view, the procedure was carried out in a way that was inaccurate, non-transparent and was not sufficiently consulted with the general public. According to these organisations, the construction of the gas pipeline threatens the objectives of European climate policy and conflicts with German energy and environmental law.

Source: OSW


Releated articles

Schwedt Refinery. Picture by PCK Raffinerie GmbH.

Jakóbik: Germany is making another Nord Stream 2-like mistake at the Schwedt refinery (COLUMN)

The cautious approach taken by the German government towards the Schwedt refinery mirrors past errors seen with Nord Stream 2...
Satellite image of gas escaping from the destroyed Nord Stream 1 and 2. Picture by SpaceKnow

Schmitt: It is worth to investigate the Russian trail of sabotage on Nord Stream 1 and 2

– Whatever the outcome of this investigation and saga, however, is the clear conclusion that especially with regard to the...
Headquarters Of The European Commission. Picture by Wikimedia Commons

EC will use a Polish idea to free Gazprom’s last European prisoners

The European Commission is preparing a plan to completely stop gas supplies from Russia through Ukraine. It wants to import...

Share:

Facebook X X X