Polskie LNG is initiating a tender procedure for the expansion of the LNG Terminal in Świnoujście

0
32

Polskie LNG has published a periodic indicative notice – an official market communication about the forthcoming contract award procedure and the selection of a contractor for the expansion of the LNG Terminal in Świnoujście planned in the near future. The procedure provides for the „design and build” formula, in which the contractor for the construction of the third tank, additional process systems increasing the regasification capacity and the railway siding will be selected.

This is an important phase in the Expansion Program of President Lech Kaczyński’s LNG Terminal in Świnoujście. Currently, the two major services offered by the LNG terminal include regasification and transshipment onto tank trucks. After the expansion, the Terminal’s regasification capacity will be increased and the range of transshipment services will be extended in order to maximize the plant’s potential and create appropriate conditions for LNG market development over the coming years.
The purpose of the periodic indicative notice is to inform all prospective bidders about the scope of the planned contract and other criteria of the contractor selection procedure planned in December 2018.

– By publishing the periodic indicative notice in accordance with the provisions of the Public Procurement Law, the company has provided the prospective bidders with an opportunity to consider the proposed conditions of the tendering procedure, said Paweł Jakubowski, President of the Board of Polskie LNG. – Thus we provide the means for the companies interested in participating in the project to submit their comments and remarks, owing to which the tendering process will be complete and comprehensive.

The scope of the planned expansion of the LNG Terminal in Świnoujście includes three turn-key projects, i.e.:

• SCV project consisting in the expansion of the existing liquefied natural gas regasification system with additional two complete SCV heat exchangers (Submerged Combustion Vaporisers) with the maximum capacity of approx. 328,000 Nm3/h together with accompanying installations, thus enabling the increase of nominal regasification capacity of the LNG terminal from ~ 5 bcma to ~ 7.5 bcma.

• Tank project under which a new FCT process storage tank („Full Containment Tank”) of 180,000 m3 gross capacity will be built along with process equipment and installations necessary for operation of the new tank and its integration with two existing storage tanks system.

• Railway project which entails the construction of a new railway siding (3-track with railroad switches and approach track) together with complete facilities for LNG-to-rail and ISO-containers transhipment service comprising 12 LNG filling stations; thus providing a new functionality of the LNG Terminal – filling railway tankers and ISO containers with LNG in the onshore part of the plant.

The fourth project implemented under the Świnoujście LNG Terminal Expansion Program is the construction of a new jetty. However, this task will be implemented under a separate tender procedure.

Polskie LNG