Baltic Pipe obtained another location decision

On June 21, 2019, the West Pomerania Province Governor signed the decision on establishing the location for the construction of the Baltic Pipe infrastructure. The investment will consist in the design, construction and operation of a gas pipeline from the Płoty transmission station to the Goleniów compressor station along with the extension of the Płoty […]

Subsequent environmental decision for the project under the Baltic Pipe program

On 17 May 2019, the Regional Director for Environmental Protection in Szczecin issued a decision on environmental conditions for the developed by GAZ-SYSTEM project „Investment constituting the infrastructure necessary to service the international Baltic gas pipeline (Baltic Pipe) constituting a connection of transmission systems of the Republic of Poland and the Kingdom of Denmark – […]

ERO cancelled the application for a Gaz-System project

On 8 May 2019 by decision DRR.WRG.7128.9.2018.ŁWe the President of the Energy Regulatory Office (President of ERO) cancelled the administrative proceedings regarding the application for the approval of the incremental capacity project proposal for the market border of Poland (E-Gas Transmission System) and GASPOOL submitted by Gaz-System.

Loading